---+!! 2009年3月工程进展 ---+!! Civil Progress of March 2009 ---++ Milestones * Feb. 18: started the excavation of main tunnel #3. * Feb. 23: started the excavation of water-pit hall. * Feb. 26: started the excavation of Hall-4 * Mar. 8: finished the concrete pouring of SAB. * Mar. 12: the 1st AD SSV transported to SAB. * Mar. 14: finished the excavation of the dome of Hall-1. * Mar. 15: finished the concrete lining of access tunnel. ---++ Pictures * Lining the access tunnel: <br /> <img src="%ATTACHURLPATH%/image004.jpg" alt="image004.jpg" width='550' height='412' /> * The 1st SSV arrived in SAB.: <br /> <img src="%ATTACHURLPATH%/image006.jpg" alt="image006.jpg" width='605' height='455' /> * Road construction near the SAB: <br /> <img src="%ATTACHURLPATH%/image008.jpg" alt="image008.jpg" width='571' height='429' /> * Concrete work for pump room and water tank.: <br /> <img src="%ATTACHURLPATH%/image010.jpg" alt="image010.jpg" width='541' height='404' />
Edit
|
Attach
|
Watch
|
P
rint version
|
H
istory
:
r4
<
r3
<
r2
<
r1
|
B
acklinks
|
V
iew topic
|
Raw edit
|
More topic actions...
Parents:
CivilConstruction
Copyright © by the contributing authors, 2007-2026.
Ideas, requests, problems regarding Daya Bay?
Send feedback