2009年3月工程进展

Civil Progress of March 2009

Milestones

  • Feb. 18: started the excavation of main tunnel #3.
  • Feb. 23: started the excavation of water-pit hall.
  • Feb. 26: started the excavation of Hall-4
  • Mar. 8: finished the concrete pouring of SAB.
  • Mar. 12: the 1st AD SSV transported to SAB.
  • Mar. 14: finished the excavation of the dome of Hall-1.
  • Mar. 15: finished the concrete lining of access tunnel.

Pictures

  • Lining the access tunnel:
    image004.jpg

  • The 1st SSV arrived in SAB.:
    image006.jpg

  • Road construction near the SAB:
    image008.jpg

  • Concrete work for pump room and water tank.:
    image010.jpg


This topic: Public > CivilConstruction > CivilProgress200903
Topic revision: r1 - 2009-03-24 - WangMeng
This site is powered by the TWiki collaboration platform Powered by Perl Powered by the TWiki collaboration platform Copyright © by the contributing authors, 2007-2026.
Ideas, requests, problems regarding Daya Bay? Send feedback